In February 2020, a team of technical specialists developed and registered technical specifications for mine auxiliary winches, on the basis of which, in May 2020, permission was obtained from the Main Directorate of the State Labor Office of the Dnipropetrovsk Region to use these winches in industrial conditions. And at the end of May 2020, the first copies of mining equipment were already delivered to consumers, which have proven themselves on the positive side.
At the beginning of July 2020, on the basis of a tender, Kryvbaszhelezrudkom PJSC signed an agreement for the supply of a batch of winches, which are manufactured by Dniprovsky Pipe Plant LLC both according to its own technical documentation and in accordance with GOST.